Build in Wilton – Thursday, September 2nd
This week, we’ll continue with volunteer framing at our new home site at the corner of Russell and Maple Streets in Wilton.
Volunteer work: finish prepping windows / doors for Styrofoam insulation on the outside. Complete Styrofoam, foaming / taping joints.
Directions from NH-101A, heading WEST out of Nashua: Turn LEFT after NH-101 overpass to take the RT-101 W ramp toward PETERBOROUGH/KEENE, merging onto NH-101 (Milford bypass). Caution: temporary 45 mph speed limit for construction is being enforced 24/7. 4.9 mi to -
2. Turn LEFT onto ELM ST/NH-101. 0.8 mi to -
3. Turn (bear) RIGHT onto WILTON RD. 0.5 mi to -
4. WILTON RD becomes MAIN ST. 0.3 mi to -
5. Turn RIGHT onto RUSSELL ST. 0.1 mi to -
6. End at site on the right, corner RUSSELL ST & MAPLE ST.
2. Turn LEFT onto ELM ST/NH-101. 0.8 mi to -
3. Turn (bear) RIGHT onto WILTON RD. 0.5 mi to -
4. WILTON RD becomes MAIN ST. 0.3 mi to -
5. Turn RIGHT onto RUSSELL ST. 0.1 mi to -
6. End at site on the right, corner RUSSELL ST & MAPLE ST.
See as many of you as can make it, starting by 9:00 AM.
Completed since last Saturday:
Russell Street, Wilton: Laid out last three walls, built, sheathed, raised those exterior walls, plumbed and squared. Started applying 2″ Styrofoam insulation to exterior walls.
Upcoming events:
Russell Street, Wilton: Continue with framing. Still seeking donations / deals.
Other small projects being coordinated.
Other small projects being coordinated.
If you have any questions, call Building Committee Chairman Eric Moore at 603.620.4182.
Tags: Build, Eric Moore, Jill Dionne, New Hampshire, Wilton