Build – October 11
Wednesday, October 8th, 2008This Saturday, we’re planning three very small indoor jobs. For planning, we’ll handle them in the following order, but will consider parallel work depending on volunteer availability on Saturday.
(1) 53 Arlington Street, Nashua. Shore up basement beam that is not supporting the living area floor above
(2) 34 New Searles Street, Nashua. Add handicapped grab bars on either side of the main hallway at the top of the basement stairs.
(3) 58 Parkhurst Rd., Merrimack. Install plastic sheeting over insulation on basement ceiling to evaluate possible cause of allergies.